Badenport has successfully completed projects in a variety of construction sectors and our staff have experience gained from over hundreds more.
The Parkeston Plant is located 10kms from the township of Kalgoorlie, Western Australia and produces quicklime for the mining industry. The plant was expanded to meet increased demands generated by the introduction of laterite nickel processing plants in the Goldfields region. In addition, a new oil storage facility was constructed to supply fuel for two (2) new 30m x 4.0m dia vertical shaft kilns. Badenport was responsible for completing the civil works for the new expansion.
Badenport's scope included the following:
Total quantity of concrete amounted to 3,500m3
Works were completed with existing plant fully operational and restrictions on working area.